Aerostar signs $173 million contract for a new multistory garage at the airport: 2,600 more spaces and a 39-month build
CoquiList · With information from Aerostar Puerto Rico (comunicado vía Foro Noticioso)

The parking garage at Luis Muñoz Marín International Airport (SJU) is about to grow by more than two-thirds of its current capacity. Aerostar Puerto Rico signed a contract on Tuesday, November 10, to build a new multistory structure with 2,600 spaces, a $173 million investment the company says it will fund through its own airport infrastructure improvement program 12. Construction is estimated at 39 months, with no start date announced 12.
What was announced
The work will be carried out by CIC Construction, a Puerto Rican firm with 43 years in business, and the design is by Benítez, Ramos & Associates 23. Jorge Hernández, president of Aerostar Puerto Rico, said the signing "marks an important step toward meeting a real need of our passengers" and that the project "is not limited to adding parking," but is meant to improve operational efficiency, traffic flow, safety and connectivity 3. José Torrens, vice president of CIC Construction, called it a privilege that Aerostar trusted his team 23.
Background: an airport running short
Aerostar justifies the project by pointing to sustained growth in parking demand, tied to rising passenger and airport-user traffic 12. The announcement included no occupancy figures 1. As an interim measure, the company recently opened satellite parking served from The Mall of San Juan, with around 500 spaces 23.
The numbers
- Investment: $173 million, funded by Aerostar 12.
- New spaces: 2,600 inside airport grounds 12.
- Current capacity: the existing garage has 3,686 spaces; with the new structure, combined capacity would reach 6,286 1.
- Size: roughly 858,000 square feet of gross construction 12.
- Useful life: designed for more than 75 years, subject to inspection and maintenance, and to withstand the wind and seismic loads applicable in Puerto Rico 2.
- Timeline: an estimated 39 months, including a new vehicle bridge linking the rental car companies' maintenance area to the structure 123.
- Support infrastructure: an emergency generator, a 100,000-gallon potable water cistern and a rainwater collection system 12.
- Solar power: the structure will be prepared for a future solar installation, but panels are not part of the current scope 12.
The vehicle bridge has a practical purpose: separating rental car movements from passenger flow, which Aerostar lists among its traffic and safety improvements 23.
What it means for you
If you fly out of SJU during peak season, the announcement does not change this week's trip. With an estimated 39-month build and no start date, the new spaces will not arrive in time for this holiday season 12. What matters is that the operator acknowledges demand that the current 3,686-space garage is not meeting 12, and that the roughly 500-space satellite lot at The Mall of San Juan is the alternative already available 23.
For airport workers and rental car users, the vehicle bridge and the new structure point to fewer crossings between passenger traffic and rental car traffic 23. And for the local construction sector, it is a large contract in the hands of a Puerto Rican firm 23.
One caveat: the announcement includes no rates, and it is not yet known whether the $173 million cost will affect what you pay to park 12. That is the most useful open question for frequent flyers.
How to / Checklist
- Before you travel, check availability and parking options, including the Mall of San Juan satellite lot, on the airport's official site: sanjuanairport.com 23.
- Arrive early during high-demand dates; the operator itself admits parking demand has grown steadily 12.
- If you need to leave your car for several days, compare the garage price with the satellite lot before deciding; rates were not included in the announcement, so confirm them directly with Aerostar 12.
- If a lane closure or detour affects you during construction, note it and report it to airport management; the project includes bridge and access work, though no detours have been announced 2.
- If your company is a construction supplier or subcontractor, contact CIC Construction, which will lead the build 23.
What's next
The basics are still missing: the construction start date and the phasing schedule were not disclosed 12. Once work begins, the 39-month clock starts, putting full opening several years out 12. It also remains to be seen whether Aerostar announces rates for the new structure and whether the solar panels the building is being prepared for are ever installed 12. In the meantime, the current garage and the satellite lot remain the options for anyone flying out of SJU 23.
CoquiList summary and local context. Read the linked sources for the original reporting.